Eleven stages between a first conversation and a set of keys. Each sets out what happens and what you provide. Programme and commercial terms are agreed per project in the written contract at stage six, because they follow from the plot, the design and the season.

  1. 01

    First contact

    You call, write on WhatsApp, or send a message through this site. We establish what you want to build, where the plot is, and whether you already have drawings or a builder in place.

    What you provide

    • What you want to build
    • The town and the location of the plot
  2. 02

    Site visit

    We walk the plot: access for lorries, slope, drainage, neighbouring structures, and which services reach the boundary. Much of what determines a build cost is visible on the ground and appears on no drawing.

    What you provide

    • Access to the plot
    • Land title or purchase documents
  3. 03

    Soil investigation

    Trial pits and boreholes establish bearing capacity and water table before anything is designed. This decides the foundation, and the foundation carries everything above it. We carry out this work ourselves rather than sending you elsewhere for it.

    We carry out our own soil investigations, so this stage runs within the same programme rather than waiting on a third party.

    What you provide

    • Clear access for the drilling rig
  4. 04

    Design and drawings

    Architectural and structural drawings are produced against the soil report and your brief. Changes are inexpensive at this stage and costly later, so this is the point to settle room sizes and layout.

    What you provide

    • Your brief — rooms, storeys, how the building will be used
    • Existing drawings, if you have them
  5. 05

    Building permit

    The permit file goes to the council with the stamped drawings. The procedure and the office differ by city, and the waiting time belongs to the council rather than to the works — so the file is lodged early.

    What you provide

    • Land title
    • Identity documents
    • Council fees
  6. 06

    Quotation and contract

    A priced bill of quantities against the final drawings, then a written contract setting out scope, stage payments, programme and exclusions. Work begins on site once that is signed.

    What you provide

    • Confirmed budget
    • Signature on the contract
  7. 07

    Foundations

    Setting out, excavation, blinding, reinforcement and the foundation pour, to the depths the soil report calls for. Everything above ground rests on the accuracy of this stage.

    What you provide

    • Site access, and water where available
  8. 08

    Structure

    Columns, beams, slabs and blockwork — the frame and the walls. Reinforcement is inspected before every pour, and concrete is tested to confirm the mix reached its specified grade.

    What you provide

    • Decisions on any variation, in writing
  9. 09

    Roofing

    Roof structure, covering and rainwater goods. Closing the building in ahead of the rains is a programme decision taken months earlier, not on the day.

    What you provide

    • Choice of roof covering
  10. 10

    Finishing

    Plastering, screeds, electrical and plumbing second fix, joinery, tiling and painting. This is the longest stage, and the one where prompt decisions keep the programme.

    What you provide

    • Selections — tiles, sanitary ware, doors, paint colours
    • Timely decisions as the work proceeds
  11. 11

    Handover

    A joint inspection against a snagging list, every item closed out, then the keys, the as-built drawings and the guarantees. A building is finished when the list is clear, not when it looks finished.

    What you provide

    • Your attendance at the inspection

Start at stage one

A message or a call. Stage two is a site visit.